What information must a contract change notice contain?


By Mick O'Donnell on 23 November 2026

A contract change notice is the statutory notice a contracting authority publishes on the Central Digital Platform when it modifies a public contract under the Procurement Act 2023. Section 74 and Schedule 8 set out the legal grounds that permit a modification, while Section 75 separately requires publication of a contract change notice before the modification takes effect, unless an exemption applies. The notice is distinct from the internal variation agreement the parties sign to change the contract itself. This article explains when a notice is required, what it must contain, which exemptions apply and how it differs from a contractual variation.

What is a contract change notice under the Procurement Act 2023?

A contract change notice is a public notice, published on the Central Digital Platform, that tells the market a contracting authority intends to modify, or has modified, a public contract. It supports the Act’s transparency objective by showing how contracts evolve after award. Section 75 sets out the publication duty, and Regulation 40 of the Procurement Regulations 2024 sets out the detailed content of the notice.

The duty applies to contracting authorities that have awarded a public contract, or a convertible contract that has become a public contract, under the Procurement Act 2023. Contracts procured under the Public Contracts Regulations 2015 remain governed by the legacy regime, including regulation 72, so Section 75 does not apply to them. Transitional rules determine which regime applies to a given contract, so confirm how your contract was procured before relying on either set of rules.

Section 75 also does not apply to certain categories of contract, including light touch contracts, defence and security contracts, and other arrangements the Act specifically excludes. Check the contract type before assuming a notice is required.

Is the legal ground for a modification the same as the duty to publish?

No. Two separate questions must be answered, in order. The first is whether the modification is permitted at all. The second is whether, and how, it must be published.

The legal grounds for modifying a public contract are found in Section 74 and Schedule 8 of the Act. Only modifications that fall within a permitted ground can lawfully be made. The grounds include:

  • Modifications provided for in the contract as awarded, such as clear review clauses or options
  • Modifications that are not substantial, as defined in Schedule 8 of the Act
  • Additional or repeat goods, services or works in the circumstances the Act allows
  • Unforeseeable circumstances, within the limits the Act sets
  • Certain modifications on a permitted change of supplier, such as corporate restructuring or insolvency
  • Below-threshold modifications permitted under the Act

Section 75 is the publication step that follows once a modification is lawful. It does not make an otherwise impermissible change lawful, and a permitted change is not automatically exempt from publication.

When must a contract change notice be published?

Where Section 75 applies and no exemption is available, the contracting authority must publish a contract change notice before the modification takes effect. Section 75 does not impose an automatic waiting period after publication. The notice must simply be published before the change is made.

Section 76 separately provides for a voluntary standstill period. An authority may choose to observe one, giving suppliers time to consider the proposed modification before it takes effect. If an authority does use a voluntary standstill period, it must last at least eight working days. It is a choice, not a requirement attached to every notice, so confirm against the official guidance how it applies to your particular change before fixing a timetable.

What exemptions apply to the duty to publish?

Not every permitted modification needs a contract change notice. The Act exempts certain changes from the Section 75 duty, including some low-value and short-extension changes. Under the exemptions as set out in the official guidance, a modification may not need a notice where it is a relevant change of:

  • 10% or less of the contract’s original value, for contracts for goods or services
  • 15% or less of the contract’s original value, for contracts for works
  • 10% or less of the contract’s original term

These figures are not universal rules. They are subject to conditions and exceptions, and whether a change qualifies depends on how the modification is assessed against the contract as awarded and on the Act’s wording. In particular, the exemption does not apply to every kind of change, so do not treat a percentage as a safe harbour without checking the conditions in the Act and the official guidance. Apply the exemptions from the legislation and the guidance rather than from general assumptions.

Two points are often misunderstood. First, a change that needs no notice may still need to be recorded in the contract file and agreed under the contract’s own variation clause. Second, a modification that does not qualify under an exemption cannot be avoided simply by labelling it routine.

What information must a contract change notice contain?

The content of the notice is prescribed by Regulation 40 of the Procurement Regulations 2024. In practice a notice identifies the contract being modified and gives enough detail for the market to understand what has changed. Typical information includes:

  • The contracting authority and the contract, with identifiers linking to the original notices
  • Supplier details for the supplier or suppliers concerned
  • A description of the modification
  • The legal ground for the modification under the Act
  • Any change to the contract value, with the revised figures where required
  • Any change to the contract duration

Because the required fields are set by the Regulations and the Central Digital Platform forms, confirm the current list against the official guidance when drafting.

What is the separate duty under Section 77?

Section 77 creates a further and separate requirement. Where a modification, or the modified contract, relates to a public contract above the applicable £5 million threshold, the authority must publish the qualifying modification or the modified contract itself, generally within 90 days. This is independent of the Section 75 notice: an authority may need to publish a contract change notice under Section 75 and also meet the Section 77 duty. Check the Act and the official guidance for which modifications qualify and how the timing is calculated.

How is a contract change notice different from an internal variation agreement?

A contract change notice is a statutory transparency notice published to the market. A variation agreement is the contractual instrument that changes the terms between the buyer and the supplier. They do different jobs, and most compliant modifications need both.

  • Statutory notice: published on the Central Digital Platform under Section 75, addressed to the public
  • Variation agreement: signed by the authorised representatives of both parties under the contract’s change control clause, setting out price, timescale, scope and risk impacts

The variation agreement should still document the reason for the change, the impact on price, programme and scope, and any effect on risk, and it should be signed by people with delegated authority. Publishing a notice does not replace that agreement, and signing an agreement does not satisfy the publication duty.

What mistakes cause problems with change notices?

The most common failures are procedural. Avoid them by building the steps into your change control process:

  • Modifying the contract before publishing the notice where Section 75 requires publication first
  • Making a change the Act does not permit, then publishing a notice as if that cured it
  • Assuming the 10% and 15% figures exempt a change without checking the conditions and exceptions
  • Treating the voluntary standstill period as mandatory, or ignoring the eight working day minimum when choosing to use one
  • Overlooking the separate Section 77 duty for contracts above £5 million
  • Applying the wrong regime to a contract procured under the 2015 Regulations
  • Failing to record the legal basis for the modification in writing
  • Treating the internal variation form as the statutory notice

Keeping a central change log and tying each modification to a named contract owner prevents most of these problems. Strong supplier relationship management also helps, because early conversations make formal changes straightforward. Disciplined contract negotiation matters here too, because unchallenged variations tend to compound over a contract term. Teams unsure of their obligations can use a Procurement Act readiness assessment to test their processes.

Where can I find the official rules and guidance?

The full text of the Act is published on legislation.gov.uk, and official guidance on contract modifications and notices is available on GOV.UK. Check both for the current position before publishing, as guidance is updated as the regime beds in.

Getting contract changes right with eXceeding

Well-run change control protects value, keeps supplier relationships healthy and avoids compliance exposure. Contact eXceeding if you would like support with contract modifications and notices under the Procurement Act 2023.

Frequently Asked Questions

Does every contract change need a contract change notice?

No. Section 75 of the Procurement Act 2023 requires a notice for modifications to public contracts, but it does not apply to certain categories of contract, such as light touch and defence and security contracts, and some modifications are exempt, including certain changes of 10% or less in value for goods and services, 15% or less for works, and 10% or less in contract term, subject to conditions and exceptions. Even where no notice is needed, the change should still be agreed and recorded under the contract’s variation clause. Check the Act and the GOV.UK guidance to confirm whether an exemption applies to your change.

Is a contract change notice the same as a signed variation?

No. The notice is a statutory publication on the Central Digital Platform, while the variation is the agreement between the buyer and supplier that changes the contract terms. A compliant modification will usually need both, and one does not replace the other.

Is there a mandatory waiting period after a contract change notice is published?

No. Section 75 does not impose an automatic waiting period. Section 76 provides for a voluntary standstill period, and if an authority chooses to use one it must last at least eight working days. Confirm the position for your change against the official guidance.

Do contract change notices apply to contracts awarded under the Public Contracts Regulations 2015?

Generally no. Contracts procured under the 2015 Regulations remain governed by those rules, including regulation 72 on modifications, and the transitional arrangements determine which regime applies. Confirm how your contract was procured before choosing the rules to follow.

Can publishing a notice make an unlawful modification lawful?

No. A contract change notice is a transparency step and does not cure a modification the Act does not permit. The legal grounds for modification sit in Section 74 and Schedule 8, separate from the publication duty in Section 75. Establish the legal basis for the change first, record your assessment in writing, and take legal advice if the change is close to the line.

Is there any other publication duty for modifications to larger contracts?

Yes. Section 77 separately requires qualifying modifications, or the modified contract, to be published where the contract is above the applicable £5 million threshold, generally within 90 days. This is in addition to any Section 75 notice. Check the Act and the GOV.UK guidance for which modifications qualify.